1、Terms of Reference For Baseline Verification on Stage II HCFC Phase-out Project in PU Foam Sector in ChinaRef. No. CS- 1A. Background1. At the 19th Meeting of the Parties to the Montreal Protocol on September 17-21, 2007, the Parties agreed to adjust their commitments related to the phase-out of HCF

2、Cs. China, as an Article 5 country, should freeze production and consumption of HCFCs in 2013 and reduce HCFCs production and consumption by 10% in 2015, by 35% in 2020, by 67.5% in 2025 with the complete phase-out in 2030, while allowing for servicing an annual average of 2.5 per cent during the pe

3、riod 2030 to 2040. 2. The Stage I Sector Plan of HCFC-141b in the PU foam sector in China was approved on the 64nd Ex.Com. meeting in 2011. It aimed to completely phase out HCFC-141b consumption in the three targeted sub-sectors: (i) refrigerators and freezers; (ii) reefer containers; and (iii) smal

4、l household appliances. At present, 57 conversion projects and 6 system house projects were financed by the Stage I PU Foam Sector Plan. The 57 conversion projects, when completed, will have eliminated HCFC-141b demand of 12,969 MT out of the targeted phase-out of 14,685 MT. The remaining phase-out

5、will be achieved through the HCFC-141b ban in the three targeted sub-sectors, the ban was promulgated by Ministry of Ecological Environment (MEE) on Oct. 18, 2018. 3. The Stage II Sector Plan for phase-out of HCFC-141b in the PU foam sector in China was finalized in January 2016 by the joint effort

6、of FECO/MEE and World Bank, and was approved on the 77nd Ex.Com with the total funding of $141,471,210. Taking into account the large remaining quantity of HCFC-141b to be phased out in the sector of 40,451 MT and the readiness of the various remaining sub-sectors for conversion in relation to viabl

7、e technologies, China proposes 30% reduction in 2018, 50% reduction in 2020, and 80% reduction in 2023. Obligatory HCFC phase-out in the spray foam will be pushed back to the end of the Stage II sector plan. 3,000 MT of HCFC-141b will be produced in 2025 for the use of the spray foam in that year, i

8、f needed. As of 1 January 2026, all HCFC-141b consumption for foam manufacturing shall be banned.B. Objectives4. The objective of this project is to select an accounting firm to assist FECO in the verification of Stage II HCFC phase-out sub-project baseline HCFC-141b consumption, crosscheck of the 1

9、41b consumption with production and/or other raw materials, evaluation of the financial status and management capacity of the PU foam enterprises, and providing financial appraisal and suggestion for selection of the beneficiary enterprises. The accounting firm will be responsible for inviting techn

10、ical expert(s) of PU foam sector to assist the verification.C. Work Content5. After preliminary evaluation of project applications, it is estimated that no more than 20 qualified enterprises will be willing to participate in the phase-out projects covered by this assignment in 2019. For those enterp

11、rises, the investigation teams will carry out the on-site investigations. The financial and technical experts from the selected accounting firm will be part of the investigation team to visit the enterprises and verify the financial and technical status and baseline HCFC-141b consumption of the ente

12、rprises concerned. The accounting firm will recruit technical expert(s) and seek advices from the experts on the verifications. FECO will recommend a short list of candidate technical experts for the accounting firm.6. It is suggested that each investigation team should consist of at least one FECO

13、or association staff, one technical expert and two financial persons from the selected accounting firm. The essential materials and invoices, verification report, and financial report related to the project will be copied and filed and all the copies from the enterprises should be stamped. The detai

14、led work content for the accounting firm will include:7. Field Investigation. According to the requirements of Multilateral Fund, the financial experts will examine the eligibility of enterprises, evaluate financial data, calculate the baseline HCFC-141b consumption, and carry out the following acti

15、vities, but not limited to:1) Verify the data on enterprises establishment, proportion of Chinese investment in the corporate capital, eligibility of equipment and whether the products exported to non-Art.5 countries;2) Collect the information on the PU foam production, foam equipment and the HCFC-1

16、41b consumption in recent three years;3) Collect recent three years financial data in order to analyze the business condition of enterprises and provide information for the available counterpart fund;4) If applicable, calculate the HCFC-141b baseline consumption from the final products sold at base

17、year and compare it with HCFC-141b baseline consumption calculated from raw materials;5) Collect HCFC-141b and HCFC-141b pre-blended polyol purchase invoices in designated years;6) Collect other important information related to field investigation and selection of beneficiary enterprises, particular

18、ly considering the situation of local competitors.8. Preparation of Financial Verification Report. The accounting firm will prepare a financial verification report for each of the enterprises to be visited. The financial verification reports should consist of the results of on-site investigation and

19、 basic information of the enterprises, including but not limited to:1) Basic information on the HCFC-141b consumption in recent three years and final products produced in those years, i.e. purchasing records for HCFC-141b and HCFC-141b pre-blended polyol, calculation method used, the suppliers of po

20、lyol and MDI, quantity of annual foam production and etc.;2) The copies of business license and documents, if any, to prove the proportion of Chinese investment in the corporate capital;3) The information of foam equipment, production capacity, quantity and quality of equipment, etc. and copies of i

21、nvoices and receipts;4) Conclusions of evaluation of the financial status of the enterprises and financial ability to carry out sub-project;5) The copies of invoices and receipts or sale record for raw materials and final products;6) Other important information related to the financial verification

22、for selection of beneficiary enterprises. 9. The technical expert(s) recruited. The technical experts will help the accounting staff to identify the correct and useful information for the baseline consumption verification and the formulation of the verification reports, especially through the way of

23、 crosscheck and calculation of the HCFC-141b consumption and production volume and industry average index, etc.; and to formulate a technical verification report for each enterprise visited.D. Outputs10. The outputs of the project are financial verification reports (one for each verified enterprise)

24、. The financial verification reports should give conclusion of financial status of enterprises, appraisal of eligibility, as well as the baseline consumption of HCFC-141b, and should have appendixes which include:1) Technical verification reports prepared by experts. The content should at least incl

25、ude: a) information gathered during the verification, b) technical methods used in consumption calculation, c) suggestion on alternative technology strategy, including specific consideration on safety considerations and capability of the enterprise to cope with the new safety requirements; d) other

26、inputs provided to the accounting firm. If there is any different opinion existing between the expert(s) and the accounting staff, the technical verification report should reflect the dissenting opinion and the financial report should make judgment and final conclusion.2) The copies of essential doc

27、uments include, but not limited to: invoices and receipts or sale records for raw materials and final products, financial reports related to the project, other essential documents deemed related to the project. All documents from enterprises should be copied and filed and all the copies from the ent

28、erprises should be stamped.E. Qualification of consultant11. The procurement method of Consultant Qualification Selection will be used for this assignment. The Consultant should meet the following requirements:1) Have a project manager with at least five years of experience of carrying out enterpris

29、es financial verification and preparation of project financial verification reports with concrete successfully completed similar assignments before. Experience with ODS phase-out activities verification is preferred;2) Have the ability to customize feasible and reasonable verification plan and staff

30、 qualified financial and technical experts for the assignments;3) Being familiar with ExCom mechanism, Ozone Layer protection, and PU Foam Sector in China.4) Have conducted similar verification assignment within last 5 years. 5) Have a team consisting of at least one financial expert and one technic

31、al expert with the qualifications as specified below.It is recommended that at least three staff will be recruited for this assignment, including 1 project manager, 1 financial expert, and 1 technical expert. The 3 team members will be respectively involved in the implementation of the verification.

32、 Table 1: Personnel Qualifications*.*Note: The qualifications for the key personnel will not be evaluated during the evaluation of short list and the recommendation for negotiation.12. In order to duly implement the sector plan, taking into account, among other things, the extensive knowledge on the

33、 PU foam sector, the experience on the baseline verifications, and the same methodology applied for the consecutive verifications, FECO reserves the right to renew the contract with the successful bidder.Name of positionNo. of personnelEstimated total working daysProfessional specialty and Experienc

34、e Project Manager1 for each enterpriseCertified Public Accountant; 5 years of experience with financial appraisal or verification on Chinese enterprises; Familiar with ODS phase-out activities in PU foam sector, Financial Expert1 for each enterprise2 years of experience with financial appraisal or v

35、erification on Chinese enterprises;Technical expert1 for each enterprise20 enterprises*3perso ns*4 days (2 for field visit and 2 for reports preparation)=240 working days 5 years of experience with PU foam manufacturing or research; Capable to formulate feasible and reasonable technical verification

36、 report; Being familiar with the equipment and the alternative technologies in PU Foam Sector in China.F. Schedule13. The duration of this assignment is estimated to be one year. The number of enterprises is estimated to be 20. FECO will be responsible for reviewing the quantity and quality of the w

37、ork during the contract duration. G. Payment Schedule14. This activity could be extended up to 10 years subject to satisfactory performance by the consultant. A price adjustment clause will be included in the baseline verification contract, for which the remunerations can be adjusted every 12 months

38、. The consultant can request for disbursement every 6 months upon contract signed with FECO. The disbursement for each unit cost should be consistent with the following conditions:Table 2: Payment Schedule*InstallmentPayment ConditionPercentage of the total contract amount Estimated Pay Date First I

39、nstallment6 months after the contract signed Second InstallmentReports submission and satisfactory with FECOunit cost of one enterprise verification*actual numbers of enterprises visited and verified 12 months after the contract signed or all verification reports of designated enterprises submitted and approved by FECO.*Note: If there is any discrepancy of payment schedule between this TOR and contract, the contract content shall prevail.

展开阅读全文
相关资源
相关搜索

当前位置:首页 > 应用文书 > 教育教学

本站为文档C TO C交易模式,本站只提供存储空间、用户上传的文档直接被用户下载,本站只是中间服务平台,本站所有文档下载所得的收益归上传人(含作者)所有。本站仅对用户上传内容的表现方式做保护处理,对上载内容本身不做任何修改或编辑。若文档所含内容侵犯了您的版权或隐私,请立即通知得利文库网,我们立即给予删除!客服QQ:136780468 微信:18945177775 电话:18904686070

工信部备案号:黑ICP备15003705号-8 |  经营许可证:黑B2-20190332号 |   黑公网安备:91230400333293403D

© 2020-2023 www.deliwenku.com 得利文库. All Rights Reserved 黑龙江转换宝科技有限公司 

黑龙江省互联网违法和不良信息举报
举报电话:0468-3380021 邮箱:hgswwxb@163.com